The timeline for a kitchen renovation depends on the scope of work, but on average, it takes between 4 to 8 weeks to complete. A minor update, such as painting, replacing cabinetry doors, or upgrading appliances, may take as little as 2-3 weeks. However, a full kitchen renovation that involves layout changes, custom cabinetry, new plumbing, and electrical work can take longer.
The process typically follows these stages:
Planning and Design (2-4 weeks): This includes selecting materials, finalizing layouts, and obtaining necessary approvals.
Demolition and Preparation (1-2 weeks): The old kitchen is removed, and the space is prepped for new installations.
Plumbing and Electrical Work (1-2 weeks): Necessary wiring and pipework are installed before cabinetry and benchtops.
Cabinetry, Benchtops, and Flooring (2-3 weeks): This includes fitting new cabinets, installing benchtops, and laying flooring.
Final Touches (1-2 weeks): Painting, backsplash installation, and appliance setup complete the process.
Delays due to material shortages, custom orders, or unexpected structural issues can extend the timeline, so working with experienced professionals can help ensure a smooth renovation.
Every kitchen is different but on average, we see Gold Coast kitchen renovations taking between 6 and 9 weeks. For larger projects it is on the longer end – for small kitchen renovations it sometimes only takes a month. Contact us on 1300 020 232 to find out more about the process.